Skip to main content

DMCivil

Bayonet Head DN355/450 Pressure Main & DN450 Gravity Sewer

Project Summary

Location

Albany, WA

Capability

Client

Water Corporation

Status

Completed

Start

May 2024

End

January 2025

Download Project Report

Project Overview

An existing PVC sewage pressure main in the Albany wastewater network was proving unreliable and if left unattended, could potentially result in an environmental incident.

Water Corporation required the services of a contractor for the construction of approximately 3.9km length of new DN355 PE100 and DN450 PE100 pressure main by horizontal directional drilling (HDD) along Ulster Road, commencing east of Lower King Road, and approximately 305m length of DN375 PVC-U gravity main along North Road, by open excavation.

Given the potential for an environmental incident, DM Civil was approached directly by Water Corporation to price the scope of works as a matter of urgency, with a firm project completion date in March 2025. Designs were fast tracked with finalisation of various aspects yet to be achieved.

Aside from the construction aspects of horizonal directional drilling longitudinally under road pavements, it was the responsibility of the contractor to achieve a workable solution for traffic control along an arterial road. This was a logistical challenge due to the concurrent Albany Ring Road project which also produced traffic flows along the same route.   

After facing initial resistance from the local government authority and the local community, DM Civil demonstrated expertise in traffic management strategies and implementation.

Bayonet Head DN355/450 Pressure Main & DN450 Gravity Sewer

Significant achievements and benefits

The first task to be undertaken by the project management and engineering team was to meet with the local government authority (LGA) to discuss stakeholder management and traffic control. This was carried out during the tender phase to provide a basis for the bid submission.

The two key areas for successful delivery for the project were close liaison with and accommodation of LGA concerns and the same attention to the local Water Corporation operations unit. The LGA was approached at time of tender and the meeting allowed our team to identify areas of concern and to clarify some misconceptions of our requirements. Likewise, the local asset operators were consulted at time of tender. Having worked with some members of the team before, and with our understanding of wastewater networks, the commissioning issues were easily addressed.

Another aspect to the delivery of the project was the use of competent and reliable subcontractors. From previous works with Kier Contracting, we were confident of the HDD installation, which was a major aspect of the works. Latent ground conditions over part of the route were picked up by the drillers and these areas handled accordingly. Traffic management was also a key component of the works and our previous good experience with Denmark Traffic Management continued throughout.      

A crucial requirement to start was to secure a local laydown area sufficient for a reasonably large workforce, the full length of pipe, and a dewatering effluent treatment area, particularly for the open trenched gravity sewer along North Road. Fortunately, the project management team was able to negotiate the use of what was essentially a dog exercise park adjacent to the open cut sewer alignment on North Road and Lockyer Avenue, very close to a formal lake, for dewatering outfall.

Overall Benefit

DM Civil was able to complete an urgent project for the client ahead of time and under budget. The result of this achievement, apart from ensuring that our client guarantees the safety of the community and a key stakeholder, demonstrates that DM Civil can be relied upon to deliver critical assets on time.

 

Your Trusted Civil Engineering Partner

Our team is eager to chat about your needs and craft tailored solutions for your success.