An existing PVC sewage pressure main in the Albany wastewater network was proving unreliable and if left unattended, could potentially result in an environmental incident.
Water Corporation required the services of a contractor for the construction of approximately 3.9km length of new DN355 PE100 and DN450 PE100 pressure main by horizontal directional drilling (HDD) along Ulster Road, commencing east of Lower King Road, and approximately 305m length of DN375 PVC-U gravity main along North Road, by open excavation.
Given the potential for an environmental incident, DM Civil was approached directly by Water Corporation to price the scope of works as a matter of urgency, with a firm project completion date in March 2025. Designs were fast tracked with finalisation of various aspects yet to be achieved.
Aside from the construction aspects of horizonal directional drilling longitudinally under road pavements, it was the responsibility of the contractor to achieve a workable solution for traffic control along an arterial road. This was a logistical challenge due to the concurrent Albany Ring Road project which also produced traffic flows along the same route.
After facing initial resistance from the local government authority and the local community, DM Civil demonstrated expertise in traffic management strategies and implementation.