Welshpool Station HP Gas Pipeline Relocation

Project Summary

Location

Welshpool, WA

Capability

Client

ATCO Gas

Status

Completed

Start

November 2023

End

December 2023

Download Project Report

Project Overview

The Welshpool Station HP Gas Pipeline Relocation project for ATCO Gas required the construction of a section of DN150 carbon steel high pressure gas pipeline to AS2885 standards. The purpose of the project was to realign the pipeline in order to make way for the demolition of the train station and modification of the adjacent train line.

ATCO Gas contacted DM Civil for pricing, and highlighted the need for an expedited schedule in order to ensure the overall program for the station demolition was not delayed. The built-up area and simultaneous works with multiple contractors working on the rail project contributed to a sense of urgency, as even a small delay in the pipeline relocation would compound into a major issue.

After a constructability workshop with our client and considering DM Civil’s success installing high pressure steel gas pipelines in difficult areas on previous projects, ATCO Gas entrusted DM Civil with the projects execution.

Despite latent conditions and expanded scopes of work, DM Civil completed the project on time.

DM Civil’s depth of experience in gas pipeline construction in difficult areas was sought by ATCO Gas to deliver this difficult project. Despite the difficulties faced, and increased scope of works, DM Civil delivered on program. 

Barrow Island Cross Island Trenching

Significant achievements and benefits

Within minutes of commencing excavation, DM Civil unearthed a buried mass concrete block directly on the alignment. As the alignment could not be modified, DM Civil acted quickly to mobilise rock breaking equipment to deal with this latent condition.

After commencing the project, our client ATCO Gas, was faced with a problem: the proximity of the pipeline to the major infrastructure project about to take place. Concerned with the effect this would have on the pipeline’s integrity, ATCO Gas workshopped enhanced pipe protection measures with DM Civil that could be incorporated within the project’s short timeframe. The outcome was the use of STOPAQ protective overwrap applied to the pipeline, and a series of concrete slabs above the pipeline, to provide mechanical protection. DM Civil acted quickly to procure and install the additional protective measures, within the project timeframe.

The presence of multiple other contractors on the small site contributed to the difficulty of the project. Excavation and backfill was sequenced such that access could still be maintained for critical works around the site for other contractors. DM Civil worked with the client and other contractors to efficiently adjust works to suit, without the need for delays in schedule.

A number of unknown services and clashes with the overall station design were identified during the works, presenting some last-minute challenges. DM Civil worked with the client to modify the configuration of bends along the alignment to reduce depth of cover to avoid these, and utilized shoring to hold up the runny sands present on site. Quick actions from the team helped to mitigate schedule delays as a result.

Overall Benefit

Our client ATCO Gas often requires the services of experienced pipeline contractors to carry out construction in difficult areas and on strict timelines. DM CIvil’s reputation and prior experience not only won the job, but also delivered on time.

 