DMCivil

Carine Rise Civil Works

Project Summary

Location

Carine, WA

 
Capability

Land Development

Client

Cedar Woods

Status
Start

July 2013

End

March 2014

Download Project Report

Project Overview

Carine Rise is a keynote development located on the former Carine TAFE site near the intersection of Reid Highway and Marmion Avenue, 15km north of the Perth CBD.

This 7.93ha site was redeveloped by Cedar Woods together with their project partners, Landcorp and the St Ives Group. The redevelopment incorporates residential lots, townhouses, apartments, residential aged care, a retirement village and mixed use development.

The works entailed the demolition of onsite structures, car parks, perimeter fencing, removal of 2km of asbestos piping, earthworks including clearing, with the retention of significant trees, extensive cut to fill and imported fill. There was also 2.7km of retaining walls, together with 36 decorative stair entries, piers, uniform open steel fencing and limestone screen walls. The roads and footpaths were extensive, spread out over the entire site with asphalt and kerb construction together with large brick paved road and footpath pavements. The underground works included the installation of two large Stormtrap precast modular stormwater detention basins together with sewer, stormwater, water, power, gas & NBN underground service installations.

As primary contractor, DM Civil was able to successfully manage and construct all civil components of Carine Rise.

Significant achievements and benefits

Residents were located on the North and Eastern boundaries of the work site. As a result, managing dust throughout the works was critical to minimise the impact on these residents. Through good construction practices and monitoring weather conditions, dust was never recorded leaving site and no complaints were raised for the duration.

The western half of the site contained loose sand to a depth of approx 3m. This material was unsuitable for building homes or services due to its relative low strength. Original option was to dig out this material, replace and compact in layers to meet geotechnical requirements. This would have been time consuming and expensive. DM Civil implemented an alternative compaction method called High Density Impact Compaction.

Using a specialised high impact roller, the 3m of loose sand could be compacted from the surface, providing the solid foundation required without any excavation and replacement of material required.

The new sewer reticulation was originally designed to connect with an existing main sewer at a depth of 6m. With the high water table, constrained site and for environmental considerations, the ground water extracted could not be disposed offsite. Through liaison with the consultant and Water Corporation, an alternative solution was found whereby an internal drop was used to connect with the existing sewer allowing the design levels to be brought up by approx 1.8m. This was significant in reducing the ground water encountered, reducing the environmental impact of the works.

An existing pre-school was operating at the eastern end of the site. To provide an event for the children, DM Civil organised a site visit where all the kids could get close access to the heavy machinery and see the works in action. This was the highlight of their week.

By providing alternative construction methods, implementation of new design principals, presenting strong community liaison skills and tight management structure, DM Civil ensured this project was a success for the client LandCorp.

Your Trusted Civil Engineering Partner

Everything should be as simple as it is, but not simpler as you