Bullsbrook Pumping Station Diversion to Ellenbrook
With significant population growth in the Bullsbrook area, the wastewater treatment facility at Bullsbrook is to be decommissioned, with flows diverted to Ellenbrook.
-
Client:
Water Corporation
-
Location:
Bullsbrook / Ellenbrook
-
Construction Period:
June 22 – Jan 24
Project overview
DM Civil was engaged to carry out these works which include:
- Upgrade of the existing Bullsbrook North Avenue wastewater pumping station (BNPS) with additional storage;
- Construction of a new Type 90 wastewater transfer pumping station (TPS) with emergency storage;
- Construction of 8.2 km of sewer pressure main and gravity main from BNPS to the new TPS including a trenchless crossing of Great Northern Highway and 800m of trenchless crossings of existing waterways;
- Construction of 5.0 km of DN400 PE100 sewer pressure main from TPS to Rose Street, including the trenchless crossing of the ARC Rail track and 900m of trenchless crossings of existing waterways;
- Construction of 1.6 km of dual pressure main (DN400 and DN315) in a common trench from Rose Street to Chateaux Place including a dual trenchless (HDD) crossing of the Ellen Brook;
- Construction of 920 m of DN450 and DN600 GRP gravity sewer from Chardonnay Place to Millhouse Road SPS.
DMC worked with Water Corporation to offer an alternative design for the pipeline route to minimise vegetation clearing and to increase protection measures adjacent to the existing live water supply pipeline.
Significant achievements and benefits
DMC worked with Water Corporation to offer an alternative design for the pipeline route to minimise vegetation clearing and to increase protection measures adjacent to the existing live water supply pipeline.
There were strict environmental constraints to be managed including:
- Maximum of 1 hectare of native vegetation clearing;
- Construction adjacent to threatened ecological communities;
- Construction adjacent to Western Swamp Tortoise protected habitat;
- Construction adjacent to protected Banksia habitat;
- Crossing of Ellen Brook;
- Crossing of ARC rail freight line; and
- Significant construction along MRWA operated Great Northern Highway.
The transfer pumping station constructed near the middle of the route between Bullsbrook and Ellenbrook, was a Type 90 (3.0m Diameter) plastic lined wet well approximately 9m deep with 370m3 of emergency storage. Construction of the pumping station was programmed and completed between January and March when the local groundwater table was predicted to be at its lowest. This minimised the amount of dewatering required for installation of the wet well and storage.
The dual horizontal directional drill (285m of DN400 and DN315) presented additional challenges with the complexity of the works and the environmental constraints around crossing a significant waterway. On commencing the HDD works, concerns were raised regarding potential fracking of drill mud and its potential to impact the waterway. DMC, along with its HDD contractor, Kier Contracting, redesigned the profile of the river crossing to complete work without any impact on Ellen Brook.
DMC scheduled and resourced the works such that that the impact to the environment and motorists on Great Northern Highway were minimised and the majority of the high impact works were completed prior to being affected by inclement weather.